    Building permit fees.

    (1)

    One-family, two-family, and multiple single family (townhouses) residential use groups:

    a. New construction (per unit for two-family and multiple single-family dwellings) 700.00 plus $0.20 per square foot
    b. Additions (per unit for two-family and multiple single-family dwellings) 350.00 plus $0.15 per square foot
    c. Remodeling (per unit) 100.00 plus $0.10 per square foot
    d. Temporary to start construction 10 percent of full permit fee, not to be applied to the full permit fee
    e. Moving of existing one- or two-family structure 650.00
    f. In-ground swimming pools 350.00
    g. Detached garage up to 750 square feet with electrical 150.00
      Detached garages over 750 square feet with electrical 300.00
    h. Demolition 100.00
    i. Permanent above-ground swimming pools with electric 150.00
    j. Conditional certificate of occupancy when requested by the builder when circumstances
    Do Not warrant
    200.00 (non-refundable)

     

    (2)

    Multiple-family residential use groups:

    a. New Construction $400.00 per unit plus $0.20 per square foot for total structure floor area
    b. Additions $325.00 per unit plus $0.20 per square foot for total addition floor area
    c. Remodeling 200.00 (per unit or area remodeled) plus $0.10 per square foot for remodeled floor area
    d. Temporary to start construction 25 percent of full permit fee, not to be applied to the full permit fee
    e. Moving of existing multiple-family structure 650.00
    f. In-ground swimming pool 350.00 plus $0.20 per square foot
    g. Demolition (of entire structure roof to foundation; not a routine part of remodel) 25 percent of new construction fee (above) minimum fee of $100.00
    h. Detached garage up to 750 square feet with electrical 

    Detached garages over 750 square feet with electrical
    150.00 

    300.00
    i. Conditional certificate of occupancy when requested by the builder when circumstances
    Do Not warrant
    50.00 per unit (non-refundable)

     

    (3)

    All other use groups:

    a. New construction $850.00 plus $0.25 per square foot
    b. Additions 700.00 plus $0.25 per square foot
    c. Remodeling 400.00 plus $0.15 per square foot
    d. Temporary to start construction 25 percent of full permit fee, not to be applied to full permit fee
    e. Moving of existing primary structure 650.00
    f. In-Ground Swimming Pools 350.00 plus $0.20 per square foot
    g. Demolition (of entire or part of structure from roof to foundation; not a routine part of a remodel) 25 percent of new construction fee (above) Minimum fee: $100.00
    h. Conditional certificate of occupancy when requested by the builder when circumstances
    Do Not warrant
    200.00 (non-refundable)

     

    (4)

    Miscellaneous permits (includes plan review fee.)

    Miscellaneous permits* $100.00

     

    * Examples: Decks, fences, gazebos, reroof of primary structure, detached garage without electric, residing, sheds, new plumbing, new electrical and/or electrical service upgrades, electrical service to detached accessory structure, porches, moving accessory structures, enlargement of an existing exterior staircase, installation of new powered roof vents/attic fans/whole-house fans, sprinkler system for one- or two-family dwelling, public sidewalks, driveway approaches, etc.

    (b)

    Voided permits: In the event a permit holder requests to have a permit voided after payment and issuance of said permit, the permit holder shall pay 25 percent of the permit fee and the entirety of any plan review fee assessed when the permit was issued. This amount shall be withheld from the refund. In the event a request for permit is voided prior payment for the permit, the permit applicant shall pay the entirety of any plan review fee assessed and a $100.00 administrative fee. (For plans approved under a master set of plans, the plan review fee for the original design model for the relinquished permit shall be paid, regardless of the number of structures built to that design, along with the $100.00 administrative fee.)

    (c)

    Hourly rate: $100.00 per hour or any part thereof, per person for any meeting, reinspection, or property maintenance related item. Minimum charge: $100.00 for meeting or reinspection; $200.00 for property maintenance/per day.

    (d)

    Plan review fees. Should any permit application be withdrawn after any of the following plan reviews has/have been completed, the applicant shall be responsible for payment of all plan review fees.

    (1)

    One- and two-family residential:

    a.

    New construction or additions: Ten percent of building permit fee. For developments utilizing a master set of buildings plans, this fee shall be assessed to the first structure built using an approved master plan and the first structure using each variation of the same approved master plan. Any deviation from the master plan or its approved variation will require a separate plan review.

    Minimum plan review fee: $125.00/dwelling unit.

    b.

    Remodeling: Ten percent of the building permit fee.

    Minimum plan review fee: $50.00/dwelling unit.

    c.

    Demolition: $50.00.

    d.

    In the event a permit application is withdrawn after completion of the plan review, the applicant shall pay the complete plan review fee.

    (2)

    Multiple-family residential:

    a.

    New construction: Ten percent of building permit fee. For developments utilizing a master set of buildings plans, this fee shall be assessed to the first structure built using an approved master plan and the first structure using each variation of the same approved master plan. Any deviation from the master plan or its approved variation will require a separate plan review.

    Minimum plan review fee: $375.00.

    b.

    Additions: 20 percent of the building permit fee:

    Minimum plan review fee: $200.00.

    c.

    Remodeling: 30 percent of the building permit fee:

    Minimum plan review fee: $200.00.

    d.

    Electrical, energy, mechanical, and plumbing plan reviews for new construction or single item project, each: Ten percent of building permit fee—Minimum fee $100.00.

    e.

    Demolition (of entire unit/structure)—25 percent of new construction fee: above.

    Minimum plan review fee: $75.00.

    f.

    In the event a permit application is withdrawn after completion of the plan review, the applicant shall pay the complete plan review fee.

    (3)

    All other use groups.

    a.

    Building code (with accessibility code) plan review fees for new construction:

    Building Size Fee
    1 to 60,000 cubic feet $375.00
    60,001 to 80,000 cubic feet $425.00
    80,001 to 100,000 cubic feet $525.00
    100,001 to 150,000 cubic feet $575.00
    150,001 to 200,000 cubic feet $675.00
    over 200,000 cubic feet $675.00 + $6.75 per 10,000 cubic feet over 200,000

     

    Refer to fire systems for additional fees for fire suppression/alarm systems.

    b.

    Electrical, mechanical, and plumbing plan review fees for new construction:

    Each of the three plan reviews is 25 percent of building code plan review fee for new construction:

    Minimum plan review fee per type: $95.00

    c.

    Energy conservation plan review fees:

    Each review is 25 percent of building code plan review fee for new construction:

    Minimum plan review fee: $95.00

    d.

    Building shell: For any speculative structure with unfinished tenant areas, the plan review fees are calculated as for new construction, above.

    e.

    Tenant build-out: Fee calculations are the same as for "new construction" for a new tenant area designed for placement in a building shell. Fees for tenant areas fully-designed and shown with the main building are included in the review fees for the main building. Minimum fees are as stated above.

    f.

    Tenant remodels: For reviews for tenant areas in existing areas to be remodeled, the "remodeling" fee calculations will apply. Minimum fees are as stated above.

    g.

    Remodelling plan review: 50 percent of the new construction plan review fees listed above:

    Minimum plan review (all codes): $250.00.

    Minimum plan review for each type of code remodel: $95.00.

    h.

    Demolition plan review fees:

    Each review is 25 percent of building code plan review fee for new construction:

    Minimum plan review fee: $95.00.

    NOTE: Fire detection/alarm systems and fire suppression systems are extra fees above the "new construction, addition, or remodel" plan review fees.

    (4)

    Fire detection/alarm systems:

    $125.00 per 10,000 square feet of floor area: Minimum fee: $125.00.

    (5)

    Fire sprinkler system plan review fees:

    Number of Sprinklers Scheduled or Calculated
    1 to 25 $75.00
    26 to 100 $250.00
    101—200 $500.00
    201—300 $550.00
    301—400 $600.00
    401—500 $650.00
    Over 500 $700.00
    PLUS, for each Sprinkler over 500: $0.95/each

     

    (6)

    Alternate fire suppression systems:

    a. Standpipe
      (No charge with sprinkler review)
    $175.00 per standpipe riser
    b. Specialized extinguisher agent
    (Dry or other chemical agent)
    $125.00 per 50 pounds agent
    c. Hood and duct cooking extinguisher agent $150.00 flat rate per system

     

    (7)

    General information: Turnaround time for all plan reviews is 15 business days—if all necessary information is provided; however, normally they are done in five to ten business days, depending upon size of the structure. If special handling is required, such as rush reviews or a preliminary review, they will be charged at the hourly rate plus the applicable fee. Second reviews are included—no extra charge. Additional third or more reviews, and when hourly rates are applicable, are charged at the hourly rate of $100.00/hour. If a completely new design set of plans is submitted for a specific address after previous design plan has been reviewed, a new plan review fee will be charged. If any plan has to be sent to an outside consultant other than the inspection firm, the outside consultant's fee(s) will be charged and that fee paid directly to the outside consultant.